School Board Refines Route 3A Appeal
By Valerie Cury
The Loudoun County School Board has filed two new motions with the Virginia Supreme Court as it continues its effort to halt construction of Dominion Energy’s approved Golden-to-Mars transmission line across school property while its appeal moves forward.
The filings, submitted Aug. 4, ask the Court for permission to file an additional reply brief responding to Dominion Energy’s July 31 opposition to the School Board’s emergency request for a stay. If granted, the reply would become part of the record the Court considers when deciding whether to temporarily stop work on the project during the appeal.
School Board Says Dominion Raised New Issues
Because Virginia Supreme Court rules generally prohibit additional briefing after a response is filed without permission from the Court, the School Board first requested leave to submit the reply. The Board argues that Dominion’s response introduced several new legal arguments and factual claims that deserve a response before the Court rules.
Among those new issues, the School Board says Dominion characterized the appeal as seeking an advisory opinion about a future condemnation case rather than challenging the State Corporation Commission’s existing approval of Route 3A.
The Board also argues Dominion introduced new evidence, including declarations regarding electric reliability, allegations of “unclean hands” and laches, and a request that the Court require a $50 million bond if a stay is granted.
Focus Remains on Route 3A
In its proposed reply, the School Board emphasizes that its appeal is directed at the SCC’s June 29 Final Order selecting Route 3A—not at any future eminent domain proceeding.
According to the filing, the approved route now crosses a parcel acquired by the School Board before the SCC issued its final decision, creating what the Board calls a “present controversy” rather than a hypothetical future dispute.
The filing argues that because the approved transmission route now crosses School Board property, the Court can still provide meaningful relief by vacating or remanding the SCC’s order for reconsideration.
Seeking Limited Protection
Rather than asking the Court to stop the entire Golden-to-Mars project, the School Board proposes a narrower form of relief.
The Board asks the Court to preserve Dominion’s own representation that it will not enter, clear, grade, construct on or acquire an interest in the School Board parcel until it has obtained any required legal authority.
The School Board argues that formalizing those assurances in a court order would protect the property while allowing construction activities elsewhere along the project to continue.
The filing contends that Dominion has not demonstrated that temporarily protecting a single parcel would delay the project’s overall schedule or threaten the company’s planned June 2028 completion date.
Challenging Dominion’s Arguments
The reply also rejects Dominion’s claims that the School Board acted inequitably by acquiring the property after the routing process had begun.
The Board argues that the property transfer was lawful, publicly approved and recorded before the SCC issued its final order. It further contends that it acted promptly by seeking reconsideration, requesting a stay and filing an appeal after acquiring the parcel.
The School Board also disputes Dominion’s request that any stay be conditioned on a $50 million bond, arguing the figure is based on the estimated cost of the entire transmission project rather than any parcel-specific delay that could result from the limited relief being requested.
What Happens Next
The Supreme Court must first decide whether to grant the School Board permission to file the additional reply. If it does, the justices will then consider the reply along with the previously filed motions and responses when determining whether to issue an emergency stay pending appeal.