Milling and paving work to take place in Leesburg
September 10, 2024/Comments Off on Milling and paving work to take place in Leesburg
As part of the Town of Leesburg’s annual street re-surfacing program, the following road segments are scheduled for milling and paving work beginning the evening of Monday, Sept. 9, through Thursday, Sept. 19:
- East Market Street, from North King Street to Loudoun Street
- Southbound Leesburg Bypass, from Edwards Ferry Road to Fort Evans Road
Work hours will be from 7 p.m. to 7 a.m. In the event of inclement weather or mechanical breakdown, work will be rescheduled for the following evening.
Any changes to the above schedule will be advertised via notices to the Town’s website and social media. For more information, please contact Inspectors Supervisor Brian Lloyd at 703-771-2782 or blloyd@leesburgva.gov.